Set out the ground floor wall frames for units 1 to 3
You are a third year apprentice carpenter on the framing crew.
What has happened
The basement slab and ground floor slab for units 1 to 6 at Kellerman Street have cured and the surveyor has placed the control points and the building line. The Construction Manager needs the ground floor wall frames for units 1 to 3 set out and checked before the framing crew arrives on Monday. The architectural drawings show party walls on the boundary between units, wet areas with set-downs and a stair void in each unit. The frame supplier's layout gives the frame lengths and openings. Rain is forecast for the afternoon and the site diary must record the set-out check. Any dimension that does not close has to be reported to the leading hand before frames are stood.
Deliverables
- Set-out sketch with calculations and diagonals
- Site diary entry recording the set-out check
- List of discrepancies and who they were reported to
- Photographs of the marked set-out
Documents to use
Units of competency
Current on training.gov.au for the Construction, Plumbing and Services Training Package as at 10 September 2026.
CPCCCA3002Carry out setting outCPCCCA3025Read and interpret plans, specifications and drawings for carpentry workCPCCOM1015Carry out measurements and calculationsCPCCCM2006Apply basic levelling proceduresCPCCCA3004Construct and erect wall framesQualifications
CPC30220Certificate III in CarpentryWhat to look for
Evidence guide
Check the calculations against the drawings, confirm the diagonals and closure are within tolerance and that the sketch is legible enough for another carpenter to use. The site diary entry must be factual and dated. Give credit for discrepancies found and reported through the right person rather than worked around silently.