Estimate the covered play deck extension
You are the Estimator in the Estimating and Contracts team.
What has happened
Bayview Early Learning Group has asked Keystone to price a covered outdoor play deck and pergola at the rear of its Berwick centre. The drawings show a 48 square metre timber deck on stumps, a steel and timber pergola with a polycarbonate roof, balustrade, a drinking fountain and two external power points. The specification calls for a slip-resistant decking board and a balustrade that complies with the National Construction Code for childcare premises. The Estimating and Contracts Manager wants the estimate ready for review by 11 September and has asked that anything on the drawings that would not comply be flagged rather than priced silently. Subcontractor quotes are needed for the electrician and the plumber.
Deliverables
- Quantity take-off sheet
- Labour and material schedule
- Priced estimate summary with assumptions and exclusions
- Compliance issues note for the manager
Documents to use
Systems to use
Units of competency
Current on training.gov.au for the Construction, Plumbing and Services Training Package as at 10 September 2026.
CPCCBC4004Identify and produce estimated costs for building and construction projectsCPCCBC4005Produce labour and material schedules for orderingCPCCBC4012Read and interpret plans and specificationsCPCCCM3005Calculate costs of construction workCPCCBC4009Apply legal requirements to building and construction projectsQualifications
CPC40120Certificate IV in Building and ConstructionCPC40320Certificate IV in Building Project SupportWhat to look for
Evidence guide
Verify quantities against the drawings within a reasonable tolerance, check that waste and labour allowances are stated and defensible, and confirm the estimate separates subcontractor allowances from Keystone labour. The compliance note must identify at least the balustrade and slip resistance issues. Look for a clear assumptions and exclusions list that a client could read.