Investigate the trestle near miss at the library refurbishment
You are the WHS Coordinator reporting to the WHS and Quality Manager.
What has happened
At the Southern Schools library refurbishment a subcontract ceiling installer working from a trestle without a handrail lost his balance and stepped down onto a stack of carpet tiles. He was not hurt, but the ceiling grid is 2.7 metres above the floor and the work was being done from an unprotected platform. The WHS and Quality Manager has opened the event in the WHS register, stopped trestle work on the site and asked you to investigate. The subcontractor's SWMS for ceiling installation is on file but was signed three weeks ago by a different crew. The site diary shows the principal has been pressing for weekend work to finish before term four. Your report is due on 18 September.
Deliverables
- Investigation report with causes and evidence
- Corrective action list with owners and dates
- Updated WHS register entry
- Draft toolbox talk record
Documents to use
- Incident, Near Miss and Hazard Reporting Procedure Procedure
- Safe Work Method Statement Procedure Procedure
- Toolbox Talk Record Template
- Work Health and Safety Policy Policy
Systems to use
WHS Incident and Hazard Register
The register of injuries, near misses, hazards, environmental incidents and corrective actions across every Keystone site.
Site Diary and Job Register
The daily record for each construction project: weather, workers on site, work done, deliveries, inspections, delays and instructions.
Licences and Training Matrix
Tracks every worker's licences, high-risk work tickets, inductions and training with expiry dates so only qualified people do licensed work.
Units of competency
Current on training.gov.au for the Construction, Plumbing and Services Training Package as at 10 September 2026.
CPCCBC4002Manage work health and safety in the building and construction workplaceCPCCBC4008Supervise site communication and administration processes for building and construction projectsCPCCWHS2001Apply WHS requirements, policies and procedures in the construction industryCPCPCM4011Carry out work-based risk control processesQualifications
CPC40120Certificate IV in Building and ConstructionCPC50220Diploma of Building and Construction (Building)What to look for
Evidence guide
The report must separate facts from opinion, identify that the SWMS was not current for the crew doing the work, name schedule pressure as a contributing factor and put engineering controls such as a platform ladder or mobile scaffold ahead of administrative controls. Check the notifiability reasoning and that the register entry is updated with owners and dates.